At the first section of the residential complex A52, according to the planned schedule, the work is on the installation of internal engineering networks of water supply and sewerage, as well as electricity. Works on the brickwork on the front part are completed by 98%, PVC window constructions are made, the beginning of the installation is scheduled for 02.08.17. The masonry of walls and internal partitions is carried out from the 14th-17th floors.

Completed work on the construction of the excavation and piles of parking of the first section. The dismantling of the old structures of the excavation was completed. Work is continuing on the installation of waterproofing of the parking structures of the first section.

See photos in the Gallery.