The first section of the residential complex A52 is actively installing PVC windows. The masonry of walls and internal partitions of floors is completed by 98%. The brickwork on the roof is made up to 90%.

Completed work on the device of lightning protection on the roof. The installation of firefighting systems of the first section began. Installation of vertical monolithic parking structures of the first section to mark. 0.000. Work has begun on the construction of the slab of the parking floor of the first section.

Completed excavation work for the device grillage of the second section and monolithic work on the construction of grillage parks of the second section. Preparation for the foundation slab of the second section is arranged. Waterproofing works are continuing.

See more photos in the gallery.