In accordance with the planned schedule in the first section of the residential complex A52 are going to work on the internal engineering networks of water supply and sewerage, as well as electricity. The brickwork of walls and internal partitions is carried out on all floors of the section – from the 14th to the 17th.
The construction of the grounds of the parking adjacent to the first section is continuing: excavations (including the parking ramp) have been carried out and work has begun on waterproofing the structures below the mark. 0.000.
Work is being carried out on the fencing of the pit of the second stage of the residential complex. The removal of engineering networks in the building spot is being carried out. The tests of the soils of the second section have been started with full-scale piles.