  • Started installation of glass fencing on balconies and loggias
  • Tile installation in the 1st floor entrance group completed
  • We started the installation of ventilation and condensation systems in the entrance group
  • Finishing work continues in the entrance group
  • Finishing work continues on floors 6-15
  • The installation of suspended ceilings in common areas, completed on 6,11,12 floors continues
  • Installation of luminaires in common areas
  • Started to install radiators
  • Completed installation of two passenger elevators.
  • We continue the installation of the elements of the ventilated facade and aluminum structures of the upper floor.
  • We carry out work on the device exterior lighting of the facade of the building
  • Installation of cable routes power supply risers
  • Works on the device waterproofing of the roof.
  • Completed installation of aluminum doors on cold transitions.
  • Planned dismantling of the cargo lift

Section 2
  • Hydro tests of the roof
  • Installation of aluminum structures of the 1st floor of the entrance group is in progress.
  • We continue the installation of the elements of the ventilated facade
  • Completed laying of low-current engineering systems routes
  • Started finishing work (screed and plaster)
  • Began to the device decorative plaster facade (LMM)

Parking and external networks
  • Work continues on connecting the external water supply network to the house on the construction site.
  • We continue laying external engineering networks of the centralized water supply, wastewater and sewage systems
  • We continue finishing the technical premises of the parking