At the first section of the residential complex A52 the installation of PVC window constructions is carried out, installation of PVC structures of balcony blocks is started. Completed brickwork on the roof. Installation of smoke fans and fire protection systems is in progress.
The work on the construction of the slab of the parking section of the first section has been completed. In the second section, the waterproofing works of the foundations are completed.
Completed work on the arrangement of columns of parking. Work has begun on the reinforcement of the foundation slab and the parking plate of the second section.